Project showcase image for Shoring System Design - CEIL Tower Project
Shoring Works

Shoring System Design - CEIL Tower Project

Client

THE FIRST GROUP

Location

DUBAI

Completed

Nov 2024

Project Overview

Key project information

Client

THE FIRST GROUP

Location

DUBAI

Category

Shoring Works

Completion Date

November 2, 2024

Project Details

Complete project information

SAC was appointed by TFG to conduct a geotechnical study and provide a design solution for demolishing an unused manhole which obstructing the proposed shoring system for the Ciel Tower project which support excavation works ranging from 1.5 to 3 meters in depth, which located adjacent to the RTA bridge ramp in the Dubai - Marina area.

Back to Project Gallery